| Subscribe via RSS

Estimate At Completion (EAC) in Earned Value Management

- 11 comments   |   Readability Mode


Due to popular demand :) I'm covering different formulas for calculating Estimate At Completion (EAC) in Earned Value Management (EVM). The PMBOK Guide, Fourth Edition mentions four different ways of calculating the EAC. We'll review each of them and reinforce the concepts with the help of a case study.

EAC is a "forecast" of the project cost, as the project progresses. Before the start of the project, EAC is the same as Budget At Complete (BAC). However, as the project progresses, EAC may differ from BAC depending upon the project performance.

Case study: You are a project manager on a really large construction project. Your project requirement is to build a shopping mall on a square piece of land. However, due to economic crisis, the project is scaled down and reduced to building just the boundary walls !! The height of the wall needs to be a staggering 2m. As per the original estimate, it will take 1 week to build one side of the boundary and cost $1000 per side. So, your original budget (BAC) is $4000 and you have 4 weeks to complete the project. Without further ado, let's get on with laying the bricks.


Now let's look at 4 scenarios and the corresponding equations to calculate EAC.

  1. Original estimate is no longer valid. Either the original estimate was fundamentally flawed or is no longer valid due to change in circumstances (for example change in scope).

    EAC = AC + bottom-up ETC

    Let's say at the end of the Week 1, you completed one side of the wall and the cost came out to be exactly $1000. However, your customer asks you to raise the height of the walls by another 0.5m, but still complete the project within 4 weeks. You re-estimate the costs. You need to buy more raw material and hire more workers. For the side already completed, you need another $500 to raise its height by another 0.5m. For the remaining 3 sides, you need $1500 per side.

    Estimate To Complete (ETC) the remaining work = $500 + 3 * $1500 = $5000

    EAC = 1000 + 5000 = $6000

  2. The current cost performance (CPI) will continue in the future.

    EAC = BAC / CPI

    Let's say after completing the first side, you spent $1200 instead of the original estimate of $1000/side. The increased cost was due to the fact that it required more raw material to build the wall than what you originally estimated. You think that you are likely to spend $1200 for each of the remaining 3 sides as well.

    CPI = EV / AC = 1000 / 1200 = 0.833

    EAC = 4000 / 0.833 = $4800

  3. The current cost performance is atypical for future project work. Future cost performance will be in line with the original estimate.

    EAC = AC + (BAC - EV)

    Let's say after completing the first side, you spent $1200 instead of the original estimate of $1000/side. However, the extra $200 were spent because of an accidental damage to the first side. You implement a risk mitigation plan to avoid this risk for the remaining work. You still believe that $1000/side is a good estimate for the remaining 3 sides.

    EAC = 1200 + (4000 - 1000) = 1200 + 3000 = $4200

  4. Project needs to meet a deadline. This following equation takes into consideration the schedule performance (SPI) and cost performance (CPI) to date.

    EAC = AC + (BAC - EV) / (SPI * CPI)

    Let's say by the end of Week 1, you built only 1.6m (instead of 2m) of the first side (or 80% it) and you spent $1200 on it. So, basically you completed $800 (EV) of work, spent $1200 (AC) on it, when you were supposed to complete $1000 (PV) worth of work. However, you still need to complete all 4 sides in 4 weeks. You might even have to hire extra workers to meet the original schedule of 4 weeks.

    SPI = EV / PV = 800 / 1000 = 0.8

    CPI = EV / AC = 800 / 1200 = 0.66

    EAC = 1200 + (4000 - 800) / (0.8 * 0.625) = $7200

As you can see, EAC can be calculated in various ways. Any of these approaches may be appropriate for a project at any given point in time, depending upon the circumstances.

Image Credit: Flickr / Giuseppe Bognanni

Related article:

11 comments:

Vikas said...

brilliant, outstanding !!

Just in Time...

I was seriously searching to have better understanding on EAC, the article provides a good understanding of it..

Dr. PDG said...

Sorry folks, but while using BAC instead of BCWS is mathematically correct, it presupposes that no change orders have been implemented.

If you look at older formulae, the "best practice" was to use BCWS (or PV in PMI speak) with the understanding that while BCWS SHOULD always equal BAC, often it does NOT.

The reason I know this and recommend it, is I work as a contractor and I often use EVM as the basis for establishing and quantifying CLAIMS. So what I recommend is not academic theory, but practical, first hand experience.

To get a much better grasp on Earned Value than what PMI preaches, I would urge you to pick up AACE's Skills and Knowledge of Cost Engineering, 5th Edition. Chapters 13 and 14 cover Earned Value in much more detail than what PMI has covered in their Manual of Practice.

BR,
Dr. PDG, Jakarta
http://www.getpmcertified.com

Brain Washer said...

Hello Dr. PDG,

Thanks for your feedback. I'll try to learn more on this subject, though I don't think I completely understood your point. It would be great if you could point us to some online reference material. As usual, I appreciate your comments.

On the lighter side, I think people are learning to walk here and you are asking them to take on skateboarding.

Thanks :)

Anonymous said...

Sir,
I have seen an equation AC+(BAC-EV)/CPI.. Not sure when it used or is it really required. Please can you explain

Harwinder said...

@ Anonymous:

That's an excellent question. I think I've seen that formula too, but never really gave it a serious thought until today when you brought it up.

Let me try to answer it with 2 simple tricks.

1. Consider EAC formula #4 above. What if I don't need to meet a deadline? In that case, I don't need to worry about SPI. So, if I substitute SPI = 1 in formula #4, I'll get the same formula that you are referring to, i.e. EAC = AC + (BAC - EV)/CPI.
Easy, isn't it?

2. Now let's do some math tricks with this to have more fun.

EAC = AC + (BAC - EV)/CPI
=> EAC = (AC*CPI + BAC - EV)/CPI ... (a)

We also know that CPI = EV / AC
=> EV = AC*CPI ... (b)

Now substitute EV from (b) in place of AC*CPI in (a), and we get
=> EAC = (EV + BAC - EV)/CPI
=> EAC = BAC/CPI

Isn't this same as EAC formula #2 in my blog post?

CONCLUSION:

When we don't worry about meeting specific deadlines (schedule performance), EAC formula #4 becomes the same as EAC formula #2. And both #2 and #4 will become the same as the formula that you referred. Basically, in this case, we only consider the cost performance.

It is important that you understand the situation and apply the appropriate formula.

I might in fact do a separate blog post just on your question. Thanks for bringing this up. It shows that you are a keen student.

If you have more questions, feel free to post them. I believe that there are no dumb questions. If you have a doubt, it's likely that many others might have the same doubt too.

All the best.

Preetham said...

Excellent. Thanks for prompt and excellent response

Preetham said...

Excellent. Thanks for prompt and excellent response

Chelluri said...

Harry .. Excellent explanation and workaround.. Thanks for this info.

Amir said...

Hi Guru,
Who ever you are, you are the best person in explaining the PMP concepts in a great way, and in continuation to that this post is indeed a great asset.
I have one question for the formula no 3.
you have mentioned it:
EAC=AC+(BAC-EV).
While in PMBOK4, It is
EAC=AC+BAC-EV.
And I think in Mathematics the preference of calculation is in the following order of preference:
Bracket
Divide
Multiply
Add
Minus.
and since you have mentioned (BAC-EV)in bracket so that got the highest preference in calculating the equation first..
Don't you think it will change the whole course of the calculation, if its done the other way, meaning adding AC+BAC first.

Can you please explain...

Harwinder said...

Hello Amir,

Thanks for your compliments :)

You are referring to the BODMAS rule. For simple addition and substraction, it doesn't matter which you do first. The brackets have been used just to show a logical segregation between the two components. The end result will be the same no matter in which order you perform the calculations.

So, you could do (AC + BAC) - EV or (-EV + AC) + BAC or any other combination and you'd get the same answer. Don't just take my word, try it out.

The BODMAS rule will come into play in equation 4 though, where you'd have to do division before addition.

Hope it helps.

Mian Amir Abbas Kaka Khel said...

Thanks Man.

Its clear now. Yes I refer to BODMAS.

I am really grareful for all your contribution. I have read all your posts and I understood all the concepts that you have explained very well. The best thing is that they are for free to us.

Beleive me I am not buttering but your explanation of all these topics are so impressive that with one read a person gets into the depth.

I will appear on Wednesday most propably and will share the LL.
Uptil now, I am stuck with 60% on all the Mock Exams for the past Two Months and now as I have understand the Earned Value concepts, Thanks to you. May be I score better....

Thankyou very much..

Post a Comment

Most Popular Stories Voted by Readers (New)

 Vote by clicking the "Recommend it" button available at the bottom of each article.

New PMP Exam Preparation Tool for PMBOK Version 4


This tool has been developed by Cornelius Fichtner (PMP) the principal instructor of the best-seller PM Prepcast. The package includes:

  • 1,750 PMP Exam eFlashCards.
  • Bonus Item 1: Three sets of 167 ITTO eFlashCards.
  • Bonus Item 2: Demystifying the PMBOK® Guide Email Course.
  • Bonus Item 3: Access to Exam Discussion Forums.
  • For PMP and CAPM
  • Based on PMBOK Guide 4th Edition standard
  • eFlashCards can be used on a computer or "any" modern device like iPod, iPhone, Blackberry, Treo and most "smart phones".
  • One year unconditional money-back guarantee

You can get this tool here for $29.99.




Recent Posts

Recent Comments

Mission Statement

Help Project Managers achieve and maintain their PMP® Certification through self-study in the most effective, efficient, ethical and economical manner.

Follow this Blog

About Me

My Photo
Harwinder
An IT Project Manager and a certified PMP. A 'Simplifier by Nature', who likes to invent simple solutions to complex problems. I blog to learn, and share what I learn.
View my complete profile

Contact Me

PMI, PMP, CAPM and PMBOK Guide are trademarks of Project Management Institute Inc.

Poll

Poll

Poll